Sunday, March 20, 2011

Creek Project Update-March 20, 2011

We have managed to install the electrical conduit from the transformer near the pump station across holes #2 and #10 and down to the area on the right side of hole #15. Next weekend we will cross hole #15 to the well then up to the halfway house. The rocks we encountered crossing hole #10 were tough as can be seen in the photos on the previous post.

With good weather sod should be laid alongside the creek slopes on #13, #14 and #15 this week. The electrical rack that will be placed next to the well is on-site and hope to place this week as well. The plan is to re-install the cart path that was torn out on hole #14 along with anywhere else the concrete has been damaged throughout the course. This should be completed by April 4th with continued good weather.

Please do not hesistate to contact me with any questions or comments regarding this project.